Substation Construction, P&C Testing and Commissioning

Project Type: 

Transmission/Distribution

Location:

Port Orange, FL

Storm Restoration Work

IMG_1837.JPG

Scope of Work

BIC provided substation field services for repairing and replacing equipment at a three, 45MVA 115KV/13.8KV power transformers at substations affected by Hurricane Ian. Services included substation physical construction and P&C testing and commissioning (relay settings implementation, relay testing, field apparatus testing, field operational checks, SCADA (RTU) and telecommunications for power transformers and feeder breakers)